Road Estimation Approaches

Road Estimation Approaches For the calculation of earthwork in roads longitudinal section and cross-section of the ground are taken and the formation line is fixed. The formation line is fixed in consideration of floods, gradient, height of bank, depth of Continue reading Road Estimation Approaches

Summary of Construction Activities with units

Summary of Construction Activities with units Sr. No. Item Units of measurements in MKS Units of payments in MKS Units of Payment in FPS 1 Earth Work Cu.m Per % Cu.m Per % cu.ft 2 Concrete in foundation P.C.C Cu.m Continue reading Summary of Construction Activities with units

Estimation, Types of Estimates

Estimation, Types of Estimates Estimation, Types of Estimates             For all engineering works it is required to know beforehand the probable cost of construction known as estimated cost. If the estimated cost is greater than the money available then attempts Continue reading Estimation, Types of Estimates

Percentage of Bricks and Mortar in a Masonry Wall

Percentage of Bricks and Mortar in a Masonry Wall By Jahanzaib 16-3-2015 Case 1: When thickness of the wall is 4.5” and that of mortar is 12mm, having the following plan. In this case Height of the wall along with the Continue reading Percentage of Bricks and Mortar in a Masonry Wall